House map approval in Karnataka

In Karnataka the local body sanctions your house plan: in Bengaluru the Commissioner of your Greater Bengaluru Authority city corporation, online on the Nambike Nakshe portal; in other cities and towns the city corporation or municipality, online on the state's Nirman-2 portal; and in villages the gram panchayat. In Bengaluru a registered architect or engineer files the plan for a site of up to 50×80 ft (4,000 sq ft) on Nambike Nakshe, where software checks it, and a house of ground + 2 floors (or stilt + 3) on a site of up to 1,200 sq ft, built to its approved plan, needs no occupancy certificate.

WhatsApp

Who passes your map

It depends on the kind of area your plot is in.

Who approves house maps in Karnataka
Your plot is inWho approvesHow
Greater Bengaluru (Central, North, South, East and West city corporations)The Commissioner of the city corporation, on the advice of its Additional Chief Town Planner, under the Greater Bengaluru Governance Act 2024Online on Nambike Nakshe (bpas.bbmpgov.in) through a registered architect or engineer; the site needs an e-Khata, required since 1 July 2025
Other city corporations (Mysuru, Mangaluru, Hubballi-Dharwad, Belagavi, Kalaburagi and others)The Commissioner, under the Karnataka Municipal Corporations Act 1976Online on Nirman-2, the state's land and building plan approval system used by 312 urban local bodies; it was down for several weeks in January and February 2026 and is back in use
City or town municipal council, or town panchayatThe municipal council, under the Karnataka Municipalities Act 1964Through a web portal, which the Act has required since September 2025: Nirman-2
Village under a gram panchayatThe gram panchayat, under section 64 of the Karnataka Gram Swaraj and Panchayat Raj Act 1993At the panchayat or online on the Rural Development and Panchayat Raj Department's Bapuji Seva Kendra portal (bsk.karnataka.gov.in); the licence must follow the Town and Country Planning Act
Land covered by a master plan, outside city and town limitsThe planning authority, such as an urban development authority, under the Karnataka Town and Country Planning Act 1961Its written permission (a commencement certificate) is needed for building that follows the master plan; farmland must first be diverted to non-farm use

By plot size and building

The first four rows apply in Bengaluru, under the Greater Bengaluru Governance Act 2024, the Bengaluru City Corporation Building Bye-laws 2003 and the Revised Master Plan 2015 zoning rules. Elsewhere the rules come from Karnataka's Model Building Bye-laws 2017 (one set for city corporations, one for municipalities) and the local master plan, and Mangaluru has its own 2025 bye-laws. Amendments of September 2025 let the state exempt kinds of buildings from the occupancy certificate and accept plans certified by licensed professionals in other cities too. Law-firm reviews of 2026 say matching occupancy-certificate notices were issued for other city corporations and municipalities, but we could not find the official notices by 3 November 2026, so confirm with your city body.

Karnataka map approval routes by plot size
Plot or buildingWhat you needConditions
Site up to 50×80 ft (4,000 sq ft) in Greater BengaluruNambike Nakshe: a registered architect or engineer uploads the plan, software checks it against the zoning rules and bye-laws, and a provisional licence follows once the fee is paidThe final licence is due within 15 days or the plan is treated as approved; in the Nambike Nakshe 2.0 pilot areas, from 19 September 2026, a plan that passes is approved automatically in about 30 minutes
House on a site up to 1,200 sq ft in Greater BengaluruNo occupancy certificate needed (government order of 9 September 2025)Ground + 2 floors or stilt + 3 only; the plan must still be approved first and the house built to it
Plot up to 250 sq m (about 2,690 sq ft) in BengaluruHeight up to 12 m, not counting a stilt parking floor, with the smaller setbacks in the table belowZoning rules amended on 5 January 2026; in the main residential zone, where the road is narrower than 9 m the height cap is 15 m including the stilt
Deviation from the approved plan in Bengaluru (house under 15 m on a plot up to 500 sq m)Can be regularised on paying a compounding feeUp to 15% of the total setback area, but no more than half the setback on any one side; 15% of floor area ratio and 7.5% of height, with no extra floor (bye-laws amended 14 May 2026)
Deviation from the approved plan in other cities and townsRegularised only through a modified plan sanctioned by the commissioner, on a feeUp to 15% in setbacks, coverage or height (no extra floor) and 5% in floor area ratio or parking, when caused by a setting-out error or site conditions (model bye-laws amended 30 October 2025); not for a building with no sanctioned plan

Setbacks for houses

Minimum setbacks in Bengaluru for buildings up to 12 m high, not counting a stilt floor, from the Revised Master Plan 2015 zoning rules as amended on 5 January 2026; plots up to 250 sq m use this table up to 15 m including the stilt. A 30×40 ft site (about 111.5 sq m) keeps 0.9 m in front, 0.7 m at the back and 0.7 m on one side. An open staircase may stand in the setback on plots up to 750 sq m, and setbacks should be left unpaved where possible so rain can soak in. Other cities follow the zoning rules of their own master plan.

Setbacks for house plots in Karnataka
PlotFrontRearSides
Up to 60 sq m (646 sq ft)0.75 mNone0.6 m on one side
60 to 150 sq m0.9 m0.7 m0.7 m on one side
150 to 250 sq m1 m0.8 m0.8 m each
250 to 4,000 sq m12% of the depth8% of the depth8% of the width each

Common questions on map approval

Where do I apply for house map approval in Karnataka?

It depends on where the plot is. In Bengaluru you apply to the city corporation of the Greater Bengaluru Authority (Central, North, South, East or West) on its Nambike Nakshe portal, through a registered architect or engineer, and the site must already have an e-Khata. In other city corporations, municipal councils and town panchayats you apply on Nirman-2, the online system used by 312 urban local bodies. In a village the gram panchayat gives the building licence.

What is Nambike Nakshe in Bengaluru?

It is Bengaluru's trust-based online route for houses on sites of up to 50×80 ft (4,000 sq ft). A registered architect or engineer checks the site and documents and uploads the plan; software checks it against drain and lake buffers, the zoning rules and the bye-laws, and a provisional licence comes once the fee is paid, with the final licence due within 15 days. A pilot of Nambike Nakshe 2.0, launched on 19 September 2026 in selected areas, approves a plan that passes the checks automatically in about 30 minutes.

Do I need an occupancy certificate for a small house in Karnataka?

Not in Greater Bengaluru, if the site is up to 1,200 sq ft, the house is no more than ground + 2 floors or stilt + 3, and it was built to an approved plan (order of 9 September 2025). Otherwise you need one, and in Bengaluru the electricity and water boards may not give a permanent connection to a building without it. A September 2025 amendment lets the state exempt kinds of buildings in other cities too; law-firm reviews say matching notices were issued, but we could not find the official text, so ask your city body. A one-time 2026 relief for power connections closed in July 2026.

Is map approval needed for a house in a Karnataka village?

Yes. No one may build, extend or rebuild a house without the written permission of the gram panchayat, which you can seek at the panchayat or online on the Bapuji Seva Kendra portal. If the panchayat does not decide within 60 days, permission is treated as given. Panchayats must follow the Town and Country Planning Act when they issue licences, so in a village covered by a master plan the house must fit that plan too.

Who can sign my house plan in Karnataka?

Under Bengaluru's bye-laws, an architect registered with the Council of Architecture or a registered civil engineer can sign the plans for any building. A registered supervisor with a diploma can sign for a building on a site of up to 200 sq m with up to two storeys or 7 m. For structural design, an architect may sign up to 500 sq m and three storeys or 10.5 m, an engineer up to 500 sq m and four storeys or 14 m, and a structural engineer anything larger. In other cities, architects and engineers register on Nirman-2.

How long does map approval take in Karnataka, and how long is it valid?

In Bengaluru the Commissioner must decide within 30 days; after that you can ask the Commissioner in writing for an order within 15 more days, and if you then write to the Greater Bengaluru Authority's Chief Commissioner and no decision comes within a month, the plan is treated as approved. The sanction is valid for five years, and you need a plinth certificate, due within 15 days, before building above the plinth. In other city corporations a permission lapses if work does not start within two years, and in municipalities within one year.

What happens if I build without an approved plan in Karnataka?

In Bengaluru the corporation can order the work demolished or altered after notice and a hearing, seal the building, demolish it at your cost and file a criminal complaint. Ignoring a notice can bring a fine of up to 20% of the guidance value of the site and building, and breaking the Act up to a year in jail and a fine of up to ₹2 lakh. Banks may not lend for such a building. A house that keeps to the rules but was built without sanction can be approved later on a compounding fee.

Sources

PRS India: Greater Bengaluru Governance Act 2024 (Act 36 of 2025) · Greater Bengaluru Authority: Nambike Nakshe building permission portal · Deccan Herald: Nambike Nakshe 2.0 launched, 19 Sep 2026 · Deccan Herald: Nambike Nakshe rolled out across the city, 3 Sep 2024 · Deccan Herald: no occupancy certificate for houses on plots up to 1,200 sq ft, 10 Sep 2025 · Karnataka UDD: Revised Master Plan 2015 zoning amendment (setbacks), 5 Jan 2026 · Bengaluru Central City Corporation: Building (Amendment) Bye-laws 2026, 14 May 2026 · Bangalore Mahanagara Palike: Building Bye-laws 2003 · Karnataka Gazette: Municipalities and Certain other Law (Amendment) Act 2025, 12 Sep 2025 (copy) · Karnataka Gazette: Model Building (Amendment) Bye-laws 2025, 30 Oct 2025 (copy) · Cyril Amarchand Mangaldas: Karnataka OC exemption for small houses, Jul 2026 · Karnataka: Nirman-2 citizen portal · Star of Mysore: Nirman 2.0 portal down, 25 Jan 2026 · BuildWatch News: Nirman 2.0 to restart in 312 urban local bodies, 6 Feb 2026 · Construction World: one-time power connections without OC, 29 Jun 2026 · Karnataka RDPR: Bapuji Seva Kendra online services · Karnataka Municipal Corporations Act 1976 (PRS copy) · Karnataka Municipalities Act 1964 (PRS copy) · Karnataka Panchayat Raj Act 1993 (PRS copy) · Karnataka Town and Country Planning Act 1961 (PRS copy)

Every fact above comes from these sources; read how we research our guides. Spotted something out of date? Tell us on WhatsApp and we will check it against the source.

Rules change often: we check the current ones for your plot before we draw. See also house plans, the cost calculator and map approval in Uttar Pradesh, Bihar, Delhi, Haryana, Madhya Pradesh, Rajasthan, Tamil Nadu, Gujarat, Jharkhand, Maharashtra, Uttarakhand, Telangana, Kerala, Punjab, Andhra Pradesh, Chhattisgarh and West Bengal.