House map approval in Uttar Pradesh

UPOBPAS stopped taking applications on 20 June 2026; development authorities now pass maps online on FASTPAS (map.up.gov.in). A house plot of up to 100 sq m needs no permission at all, only a ₹1 online registration, and single houses up to 500 sq m in approved layouts are approved instantly.

Who passes your map

It depends on the kind of area your plot is in.

Who approves house maps in Uttar Pradesh
Your plot is inWho approvesHow
Development authority area (LDA, KDA, GDA, BDA…)The authority's Vice-Chairman, under the UP Urban Planning and Development Act 1973Online on FASTPAS (map.up.gov.in), under the 2025 bye-laws
Regulated area (towns without an authority)The prescribed authority named by the state, under the UP Regulation of Building Operations Act 1958At the regulated-area office; the 2025 bye-law relaxations do not apply
Village or town outside bothNo official rule foundAsk the tehsil or district office before you build

By plot size (development authority areas)

UP's 2025 building bye-laws, as amended on 21 November 2025.

UP map approval routes by plot size
PlotWhat you needConditions
House up to 100 sq m (1,076 sq ft)No permission: online registration with a ₹1 token and a self-certified planNot in mela areas, unauthorised colonies, or on government or disputed land; a bigger plot cannot be split to qualify
Single house up to 300 sq m, outside approved layoutsInstant online approval on paying the feesWhere the authority has notified it and the approach road is of the required width
Single house up to 500 sq m in an approved layoutInstant online approval, treated as approved when filedPlan certified by a licensed architect or engineer
Anything larger, or multi-unitFull online applicationDeemed accepted after 30 days if the professional certifies it and the NOCs are in place

Setbacks for houses

Open space to leave from the plot edge, in metres. Plots below 300 sq m may build three floors with stilt up to 15 m; larger plots four floors up to 17.5 m.

Setbacks for house plots under UP's 2025 bye-laws
PlotFrontRearSides
Under 150 sq m1 m00
150 to under 300 sq m3 m1.5 m0
300 to under 500 sq m3 m3 m0
500 to under 1,200 sq m4.5 m4.5 m1.5 m, 0
1,200 sq m and above6 m6 m1.5 m each

Common questions on map approval

Where do I apply for map approval in UP now that UPOBPAS has closed?

UPOBPAS took no new applications from 20 June 2026. Development authorities now use FASTPAS (Fast and Simplified Trust Based Plan Approval System) at map.up.gov.in, which LDA's website links to. Regulated areas take plans at their own office.

Do I need map approval for a 100 sq m house plot?

Not inside a development authority area. Under the 2025 bye-laws (amended 21 November 2025), a house plot of up to 100 sq m needs no permission, only online registration with a ₹1 token and a self-certified plan. It does not apply in a mela area, an unauthorised colony, on government or disputed land, or to a bigger plot split to qualify, and you must still follow the master plan and bye-laws.

How long does map approval take in Lucknow?

LDA moved to FASTPAS on 1 January 2026 and says homes of up to 100 sq m are approved within minutes. Single houses up to 500 sq m in approved layouts, with a plan certified by a licensed professional, get instant online approval. Other residential plans are treated as accepted if not decided in 30 days, provided the professional's certificate and the NOCs are in place.

Who can sign my house plan in UP?

The owner and a licensed technical person: a Council of Architecture-registered architect, a licensed civil engineer, or, for plots up to 200 sq m with up to two storeys or 7.5 m, a licensed supervisor.

How many floors can I build on a small plot in UP?

Under the 2025 bye-laws, plots below 300 sq m may build three floors with stilt up to 15 m, and plots of 300 sq m and above four floors with stilt up to 17.5 m.

Is map approval needed for a house in a village in UP?

It depends on where the village is. Development areas and regulated areas include many villages (Basti's authority covers 217), and there the same rules apply as in town. We found no official rule for a village outside both, so ask the tehsil or district office.

Do I need a completion certificate?

Not for a house on a plot under 500 sq m in a development authority area. Where one is needed it is issued online, and it is treated as approved if the authority does not reject it within 8 working days.

What happens if I build without an approved map?

Under the 1973 Act the authority can fine you up to ₹50,000 plus ₹2,500 a day while it continues, order demolition within 15 to 40 days after hearing you, stop the work and seal the building. You can appeal to its Chairman within 30 days. In a regulated area the prescribed authority can order demolition within two months.

Sources

UP Model Building Bye-laws 2025 (GDA copy) · UP Housing Dept: bye-law amendment, 21 Nov 2025 · UPOBPAS: suspension notice, 20 Jun 2026 · LDA: building plan approval system (map.up.gov.in) · ETV Bharat: LDA starts FASTPAS, 1 Jan 2026 · UP Urban Planning and Development Act 1973 (GDA copy) · UP Regulation of Building Operations Act 1958 (GDA copy) · Amar Ujala: 2025 bye-laws not for regulated areas, 17 Jul 2025 · GDA: map fees 2026-27

Rules change often: we check the current ones for your plot before we draw. See also house plans and the cost calculator.