Gorakhpur · Naksha pass (GDA map approval)
Naksha pass in Gorakhpur: GDA map approval
In the Gorakhpur Development Authority (GDA) area, a house map is passed online on FASTPAS (map.up.gov.in) under UP's 2025 building bye-laws. A house on a plot up to 100 sq m needs no permission, only an online registration with a ₹1 token; a house on a plot up to 500 sq m in an approved layout gets instant approval on a licensed professional's plan. Bigger or unplanned plots in Gorakhpur go through a full application.
Who passes your map: GDA, GIDA or the zila panchayat
It depends on where your plot is:
- GDA area. After a 2020 notification, 233 revenue villages and the Peppeganj, Mundera and Pipraich nagar panchayats were added to the GDA, which now covers about 642 sq km (Amar Ujala, 5 December 2025).
- Master Plan 2031. The revised Gorakhpur Master Plan 2031 has been in force since 7 March 2024. Of its 520 sq km, 465 sq km is in GDA's jurisdiction; a new master plan is being prepared for Peppeganj and the remaining 177 sq km of notified area (same report). If your plot is in that part, ask GDA what land use applies before you buy.
- GIDA area. In the notified area of the Gorakhpur Industrial Development Authority, GIDA, not GDA, issues building permits. UP's model building regulations of 12 October 2026 for industrial authorities, GIDA among them, give houses up to 100 sq m the same online registration. We found no notice that GIDA has published its own version yet, so ask GIDA.
- Villages outside both. UP's district panchayats have made map approval compulsory for building in their areas (Free Press Journal, 27 February 2026). Ask the Zila Panchayat, Gorakhpur, for its rules.
What your house needs, by plot size
These are the rules for a house under UP's Model Building Bye-laws 2025, clause 2.1.2, as amended on 21 November 2025:
- Plot up to 100 sq m (about 120 gaj): no permission is needed. You register online with a ₹1 token and self-certify the ownership, plot size, floors, setbacks, room sizes and, above 50 sq m, the parking. No completion certificate is needed. This route is not open in a mela area, in unauthorised layouts or colonies, on government, prohibited or disputed land, or for a piece split off a bigger plot.
- Plot up to 500 sq m in an approved layout (not a multi-unit building): instant online approval on a plan and certificate by a licensed technical person. The owner, the applicant and that professional are personally responsible for it.
- Plot up to 300 sq m outside an approved layout: instant approval only in areas the Authority identifies, where a government agency has built an approach road of the required width.
- Anything bigger, or over 100 sq m outside an approved layout: a full online application.
The ₹1 registration and instant approvals can be revoked within 30 days if something is wrong, and at any time if they were obtained by misrepresentation. Our Uttar Pradesh map approval guide covers the same rules for every UP development authority.
How the application runs on FASTPAS
UP's old portal, UPOBPAS, stopped taking new applications on 20 June 2026. Development authorities now take them on FASTPAS at map.up.gov.in, and in August 2026 GDA's vice-chairman told staff to clear every map pending on FASTPAS (Amar Ujala, 6 August 2026). In outline:
- Register on map.up.gov.in and file the application with the drawings and papers below.
- The plans are signed by the owner and a licensed technical person (bye-law 2.4.2). Our civil engineer is registered with the GDA (Reg. No. E 02/GDA/2015).
- A shortfall must be fixed within 15 days, and fees paid within 30 days of the demand, or the file is rejected automatically (2.7.3.1).
- With the professional's certificate and the needed NOCs, a plan not decided within 30 days is treated as accepted (2.7.2.1).
- A building permit is valid for five years and can be revalidated for up to three more (2.7.4.2).
- At plinth level you upload dated photos with GPS coordinates and an affidavit, except for plots in the Authority's own schemes and approved layouts (2.8.1.2).
The fees are set by the Authority: plan submission, scrutiny and inspection fees, betterment and external development charges (2.6). The portal works them out for your plot. In September 2025 GDA started a "Manchitra Samadhan Diwas" on the second and fourth Thursday of each month for pending maps (Amar Ujala, 20 September 2025); ask GDA whether it still runs.
Papers and drawings to keep ready
The 2025 bye-laws ask for (clauses 2.2.2 and 2.2.3):
- Ownership: the sale deed or lease deed, with a declaration and the site plan. For a plot in an Authority scheme, the possession letter; for Nazul or Improvement Trust land, the freehold deed or NOC.
- Road widening: an affidavit to hand over land if the master plan widens the road in front.
- Drawings: location plan, site plan, building plan, services plan, specifications and the certificate of supervision.
We prepare the floor plans, elevations, sections and structural drawings an application needs; see ghar ka naksha in Gorakhpur for what you get, and packages for the prices. To plan the cost of building, use the cost calculator.
Earthquake Zone IV and the structural certificate
Gorakhpur is in seismic Zone IV (IS 1893 Part 1:2016, Annex E). Under the bye-laws:
- Every house needs a structural design by a registered or licensed engineer (clause 11.1).
- More than three floors including the ground floor, or taller than 12 m: the bye-laws' earthquake-resistance rules apply, and a Structural Safety Certificate signed by the owner, the architect and the structural engineer goes with the map (11.8).
So a ground-plus-two house within 12 m needs an engineer's design but not that certificate; a ground-plus-three house needs both. Why Zone IV detailing matters even below that is in our post on earthquake-resistant house design.
Built without a map: shaman (compounding) and what cannot be saved
GDA compounds some deviations for a fee. It approved 10 compounding (shaman) maps in June 2026 and 23 in July 2026, and has demolished 135 illegal plottings so far (Amar Ujala, 6 August 2026).
The 2025 bye-laws (clause 16.3.2) do not allow compounding of construction:
- on road or park land, or against the master plan's land use;
- on plots in illegal colonies, or on government or disputed land;
- on ponds, rivers or drains shown in the records;
- in buildings where the earthquake-resistance rules are compulsory.
Check that a colony is approved before you buy a plot in it. Our post on checking a plot before the naksha lists what to ask.
Common questions
Gorakhpur me naksha pass kaise karaye?
GDA area me naksha FASTPAS portal (map.up.gov.in) par online pass hota hai. 100 sq m tak ke plot par sirf ₹1 me online registration aur self-certification. Approved colony me 500 sq m tak ke plot par licensed architect ya engineer ke naksha par turant manzoori. Bade plot ya bina approved layout wale plot par poori application lagti hai.
100 sq m (lagbhag 120 gaj) tak ke plot par naksha pass zaroori hai kya?
UP ke 2025 bye-laws ke hisab se 100 sq m tak ke residential plot par permission nahi chahiye, sirf online registration ₹1 token ke saath aur self-certified naksha. Completion certificate bhi nahi chahiye. Lekin mela area, avaidh colony, sarkari ya vivadit zameen, ya bade plot ka toda hua hissa ho to ye rasta nahi milta.
How long does GDA take to pass a house map?
A house on a plot up to 100 sq m is registered online at once. Up to 500 sq m in an approved layout gets instant approval on a licensed professional's plan. For a full application, the 2025 bye-laws treat a plan as accepted if it is not decided within 30 days, provided the professional's certificate and the needed NOCs are filed.
Is my plot under GDA, GIDA or the zila panchayat?
GDA covers about 642 sq km, including 233 revenue villages and the Peppeganj, Mundera and Pipraich nagar panchayats added after 2020. GIDA's notified industrial area has its own building permit. Villages outside both come under the zila panchayat. The village named in your khatauni and the authority's own list settle it; ask before you buy.
Do I need a completion certificate for a house in Gorakhpur?
Under UP's 2025 bye-laws as amended on 21 November 2025, a residential building on a plot of less than 500 sq m does not need a completion certificate, and the 100 sq m registration route never needs one. Larger plots do; the authority issues it online after a random check, and late applications pay more.
Can a house built without a passed map be regularised in Gorakhpur?
Some deviations can be compounded (shaman) for a fee: GDA approved 33 compounding maps in June and July 2026. Building on road or park land, against the master plan, in an illegal colony, on government or disputed land, on ponds or drains, or where earthquake rules are compulsory cannot be compounded under the 2025 bye-laws.
Sources
UP Model Building Bye-laws 2025 (GDA Ghaziabad copy) · UP Housing Dept: bye-law amendment, 21 Nov 2025 · BIS, IS 1893 (Part 1):2016, Annex E · Amar Ujala Gorakhpur: GDA area and Master Plan 2031, 5 Dec 2025 · Amar Ujala Gorakhpur: GDA on FASTPAS, compounding and illegal plotting, 6 Aug 2026 · Amar Ujala Gorakhpur: Manchitra Samadhan Diwas, 20 Sep 2025 · UPOBPAS: new applications suspended from 20 Jun 2026 · UP model building regulations for industrial authorities, 12 Oct 2026 · Free Press Journal: district panchayat map approvals, 27 Feb 2026